PERT / Dependency Network
Scroll the chart sideways to see all of it
Made-up data, for demonstration only
PERT Chart is a network diagram that shows a project's tasks as boxes, joined by arrows in the order they must be done. Use it to find which tasks must not slip. This example is a new-system project with 7 tasks (made-up data) taking 29 days in total.
How to read a PERT Chart
- Boxes are tasks and arrows are dependencies. In this example "Integration test" can start only when both "Build" and "Install hardware" are done.
- ES and EF are the earliest start and earliest finish. Here A, requirements gathering, runs from day 0 to 5. B, design, runs 5 to 12. D, development, runs 12 to 24. F, integrated testing, runs 24 to 28. G, go-live, runs 28 to 29.
- The orange line is the critical path. A → B → D → F → G is 5+7+12+4+1 = 29 days. It is the longest continuous path and it sets the total project time.
- A delay on the critical path moves the finish date at once. Tasks on this path have no spare time (slack is zero).
- Tasks off the critical path have spare time. The path A → C → E → F → G takes 5+4+6+4+1 = 20 days, so it has about 9 days of spare time. The vendor contract and the equipment installation can slip within that window without moving the finish date.
- Find the tasks to watch closely. Here "Build", at 12 days, is the longest task on the critical path. To shorten it, check whether adding resources really helps.
When to use it
- A project has many tasks that depend on each other. PERT was designed to analyse and show the tasks involved in finishing a project.
- You need to know which tasks must not run late. The critical path shows the tasks whose delay affects the finish of the whole project.
- Durations are uncertain. PERT can use three estimates (fastest, normal, slowest). This example uses one value per box to keep it easy to read.
- You are planning a large project. PERT was developed to ease the planning and scheduling of large, complex projects.
When not to use it
- You want to see a calendar and daily progress. Use a Gantt Chart.
- There are few tasks and they run one after another. Use a Timeline or a list.
- You want to show who does what. Use a Swimlane Diagram.
- You want to track the remaining work each week. Use a Burndown Chart.
Common mistakes
1. Forgetting dependencies
A task with a missing arrow makes the critical path wrong. Check that every task has its predecessors and successors.
2. Using a single duration without saying it is an estimate
This example uses one value per task. To assess uncertainty, PERT uses three values: the fastest, the most likely and the slowest. The expected value can be calculated as (fastest + 4 × most likely + slowest) ÷ 6.
3. Assuming the critical path never changes
If a task off the path runs later than its spare time, the critical path changes. Recalculate.
4. Leaving out start and finish times
Without ES and EF, readers cannot find the critical path themselves. This example shows them in the boxes.
5. Reading the coloured line as task priority
The critical path is about sequence in time, not about business importance.
Compared with similar charts
| Chart | How it differs | Choose it when |
|---|---|---|
| PERT Chart | A task network that stresses dependencies and the critical path | You plan a project whose tasks depend on each other |
| Gantt Chart | Bars along a calendar | Schedule and progress |
| Flowchart | Steps and conditions, with no time | You explain a process |
| Burndown Chart | Work remaining over time | You track a development team's progress |
History and development
PERT was developed in 1958 to help plan the US Navy's Polaris project, with support from Booz Allen.
Frequently asked questions
How is PERT different from CPM?
Both PERT and CPM use a task network and a critical path. PERT stresses uncertain durations by using three estimates, while CPM examples usually use a fixed duration per activity. Cost analysis can be added, and PERT does not rule it out.
What is slack?
Two values need to be kept apart. Free float is how far a task can slip without moving the earliest start of the next task. Total float is how far it can slip without moving the project finish or breaking a schedule constraint. In an example with no extra constraints, tasks on the critical path have a total float of zero.
When did PERT begin?
See the history section.
References
- Program evaluation and review technique · Wikipedia · en.wikipedia.orgUsed to confirm: the definition and basic facts about PERT
- Flowchart · Wikipedia · en.wikipedia.orgUsed to confirm: the definition and basic facts about the flowchart
- Project schedule risk analysis · Project Management Institute · pmi.orgUsed to confirm: the three estimates and how durations are calculated in PERT
- Critical path method calculations · Project Management Institute · pmi.orgUsed to confirm: the critical path, ES/EF, free float and total float
- Incorporating risks in schedule development · Project Management Institute · pmi.orgUsed to confirm: the origin of PERT in the Polaris project in 1958
Last updated 28 Nov 2026