Burndown Chart

FacebookX
Example: Backlog over a 10-day sprint (made-up data)Apache ECharts

Variant: Standard

Made-up data, for demonstration only

Variants

4 types · click one to see it in the frame above
Difference from standard
The recommended type; use it as a starting point
Use when
Track the work remaining in a sprint against the planned line

Burndown Chart is a chart that shows the work remaining against time. This example is a 10-day sprint (made-up data) that starts with a backlog of 40 items. The dashed line is the plan, falling in a straight line to 0. The solid line is the actual backlog.

How to read a Burndown Chart

  • The horizontal axis is days and the vertical axis is remaining work. The line falls as work is closed, but you also need to consider scope changes and how the work was estimated.
  • The dashed line is the ideal plan. It is a straight line from the full amount of work at the start to zero at the end. Here it runs from 40 to 0 on day 10.
  • An actual line above the plan means more work is left than planned. On day 5 there are 31 items left against about 22 planned, a gap of about 9. The cause may be slow progress or added work.
  • An actual line below the plan means less work is left than planned. The team may be working faster, work may have been removed, or the estimates may have been too high.
  • Check the last day. On day 10 there are still 6 items left, so the work was not finished on plan.
  • Check the slope. From day 7 to day 10 the actual line drops from 24 to 6 items, faster than at the start. The chart alone cannot say why.

When to use it

  • Tracking the progress of a sprint or a project with countable work. You see at once whether the team is on plan.
  • In a team's daily meeting. You see the trend without reading a table.
  • A rough estimate of whether the work will finish in time. Extend the trend line to zero, stating the assumption that the rate of closing work stays the same.

When not to use it

  • The scope changes along the way. When new work is added, the line rises or flattens without saying what happened. Use a burnup chart (which has a total-work line) or a cumulative flow Stacked Area Chart.
  • Work items differ a lot in size. Counting items can mislead. Use points or hours.
  • You need a schedule and dependencies. Use a Gantt Chart or a PERT Chart.
  • There is no reliable plan line. Use a Run Chart.

Common mistakes

1. A straight plan line, but real work is not straight

The straight line is only a reference. Real work tends to drop in steps. Do not read every day above the line as a failure.

2. Scope changes that are not visible

If work is added in the middle of a sprint, mark it on the chart. Try the "Cut off at today" variant.

3. Bad estimates that make the team look fast or slow throughout

If the team always over-estimates, it looks ahead of plan all the time. If it always under-estimates, it looks behind all the time.

4. Treating the forecast line as a sure finish date

Try the "Forecast line" variant to estimate the finish date, assuming the rate of closing work does not change.

5. Using it for work that is not split into items

Convert the work into a countable unit first.

Compared with similar charts

ChartHow it differsChoose it when
Burndown ChartRemaining work falls over time against a planYou track a sprint
Burnup ChartCompleted work rises, with a total-work lineYou need to see scope changes
Gantt ChartTask bars on a calendarYou need a project schedule
Run ChartA value over time with no plan lineYou want to see the general trend

Frequently asked questions

How is a burnup different from a burndown?

A burnup measures completed work on the vertical axis. The line starts at the bottom and rises, and it usually comes with a line for the total work, so scope changes are visible.

What unit goes on the vertical axis?

Time, or story points (a score for complexity), both work.

What does it mean when the line is above the plan?

There is more work left than expected. Check whether it comes from progress or from a change in scope.

References

  • Burndown chart · Wikipedia · en.wikipedia.orgUsed to confirm: the definition and basics of a burndown chart
  • Agile burndown chart tutorial · Atlassian · atlassian.comUsed to confirm: the plan line, what the backlog means, and the limits when scope changes
  • What is the sprint burndown report? · Atlassian Support · support.atlassian.comUsed to confirm: changes in scope during a sprint